In a London self build, the smart home belongs at the front of the new build timeline, not the end: the cable routes and the comms cupboard should be on the drawings before the electrician prices the job, and every low voltage cable must be in place before the walls are boarded. Plan it in that order and the technology is ready the week you move in, without chases through new plaster. This guide walks through each step and what to settle before it.
London plots bring their own pressures. A narrow infill site, a basement dug under a replacement house, a loft that becomes a bedroom, neighbours on both sides and a tight programme all leave little room for changing your mind once the build is under way. That is why the early steps matter so much here.
The new build timeline in one table
Every project is different, but the order of work is very similar from one house to the next.
| Step | Smart home task | Who leads it |
|---|---|---|
| Concept and planning drawings | Agree the systems you want and reserve a ventilated comms cupboard | You and your architect |
| Technical design and building control | Device layouts, a numbered cable schedule and a budget | You, your architect and us |
| Substructure and basement | Ducts in for broadband and any garden, gate or outbuilding runs | The groundworks contractor |
| Shell and roof | Site walk to mark positions on the real walls and ceilings | You, the electrician and us |
| First fix | All data, speaker, keypad and sensor cables run and labelled | The electrician, supported by us |
| Boarding, plastering and decoration | Cables protected and left alone | The finishing trades |
| Second fix and commissioning | Devices fitted, rack built, scenes and zones programmed | Us and the electrician |
| Handover | Training, logins, drawings and the cable schedule passed to you | Us |
Planning drawings: choose the systems, not the products
At concept stage you only need a list: Wi-Fi in every room, lighting control in the main spaces, music in the kitchen and garden, televisions, security cameras, an entry system at the front door, heating controls and perhaps motorised blinds. With that list, your architect can find a home for a comms cupboard with power and ventilation. In a terraced or semi detached London house, the space under the stairs or a corner of the basement plant room is common, but think about heat and access before you settle on it.
Building control and the technical design
Before work starts on site, building control must be told. The government's circular letter on changes to the building control process explains that, for work that is not on a higher risk building, a notice must go to the building control body at least two working days before work starts, and a second notice within five working days of the work reaching the point the regulations call commencement. For a new house that is not complex, commencement means the foundations, any basement and the ground floor structure are complete. The same letter says approval lapses automatically after three years for work that has not reached that point.
The technical design stage is also when the smart home design should be finished, because this is when the electrician is asked to price. Our post on smart home drawings for a London self build shows what the layouts and cable schedule contain, and our survey and design page explains how we produce them. With the same drawings in every tender, the quotes you compare are for the same job.
Groundworks and basements: ducts first
The groundworks are when the incoming broadband duct is laid, and on a basement build they are the only chance to bring cables through the waterproofing in a planned, sealed way. If you want lighting or speakers in the garden, a link to a garden office or a cable to a gate, the ducts go in now. Our guide to fibre broadband for a London self build covers the incoming connection.
Shell and roof: walk the rooms
Once the shell is up and the windows are in, the rooms can be walked at their true size. We meet you and your electrician on site, mark the keypads, speakers, access points, screens and sensors on the walls and ceilings, and check them against joists, steels and window heads. It is the cheapest point in the whole new build timeline to move a position, so take your time and bring your interior designer if you have one.
First fix: the cables go in
At first fix the electrician runs the mains wiring and, from our cable schedule, every Cat6, speaker, keypad and sensor cable back to the comms cupboard, each one labelled at both ends with its number. Our founder, Kieran McGuire, is an electrician, so the drawings we hand over are written with the person on site in mind. Our first fix wiring guide for London self builds lists what has to be in place, and our post on working with a smart home electrician explains who does what.
Before any plasterboard goes up, check:
- Every cable on the schedule installed, labelled and ticked off.
- Network cables tested end to end.
- Back boxes at the agreed heights for keypads, screens and the door entry panel.
- Speaker and access point positions clear of joists, downlights and fire barriers.
- A photo record of every open wall and ceiling.
Second fix, commissioning and moving in
After decoration we fit the devices, build and dress the rack, and then commission the system: lighting scenes room by room, audio zones, heating and blinds linked, and Wi-Fi tested on every floor including the basement and the garden. Our lighting design guide for London self builds helps you decide the scenes before this point.
Allow a short gap between commissioning and the removal van. A few days of living with the system almost always brings a handful of small changes, and they are quicker to make before the furniture arrives.
Questions we are often asked
How early should we bring you in?
Ideally while the technical drawings are being prepared, before the electrical work goes out to tender. That way the comms cupboard is designed in and every quote includes the low voltage cabling.
Will the smart home slow the build down?
Not if it is planned. The cables go in alongside the mains at first fix, and the fitting and programming happen while the other second fix trades are on site.
Our walls are already boarded. Can you still help?
Yes. We survey what is there and design around it, using existing cables where we can and wireless products where a new cable is not practical.
What does a first consultation cost?
A design consultation is £360 plus VAT, and extra time is £90 an hour plus VAT, as shown on our booking page.
Do we keep the drawings at the end?
Yes. The final layouts and cable schedule are handed over with the house, so anyone who works on it later can see exactly how it was wired. Our process page shows how a project runs from start to finish.